417 infra projects show cost overruns of Rs 4.77 lakh crore in Sep

417 infra projects show cost overruns of Rs 4.77 lakh crore in Sep

3 years ago
Indian wrestling coaches must keep updating: Bentinidis

Indian wrestling coaches must keep updating: Bentinidis

18 mins ago
India’s Triumph: Asian U20 Athletics Championships Medal Haul

India’s Triumph: Asian U20 Athletics Championships Medal Haul

4 hours ago
Sunil Gavaskar advises Mumbai Indians to take ‘some time off’ amid reports of Hardik Pandya sacking: ‘Take a step back’

Sunil Gavaskar advises Mumbai Indians to take ‘some time off’ amid reports of Hardik Pandya sacking: ‘Take a step back’

4 hours ago
Abhishek Banerjee’s Attack Not Same As Mamata’s In 1990, But Battered TMC Can Still Use It In 3 Ways | India News

Abhishek Banerjee’s Attack Not Same As Mamata’s In 1990, But Battered TMC Can Still Use It In 3 Ways | India News

4 hours ago
Johnson & ​Johnson prostate cancer drug reduces risk of cancer spread and death in late-stage study

Johnson & ​Johnson prostate cancer drug reduces risk of cancer spread and death in late-stage study

5 hours ago
Rahane, Iyer, Satghare among captains headline grand season launch of T20 Mumbai League

Rahane, Iyer, Satghare among captains headline grand season launch of T20 Mumbai League

6 hours ago
Sri Lanka raises fuel prices after IMF loan installment

Sri Lanka raises fuel prices after IMF loan installment

6 hours ago
‘We were called terrorists’: Rahul Gandhi meets CBSE student Vedant, who sparked questions over result evaluation

‘We were called terrorists’: Rahul Gandhi meets CBSE student Vedant, who sparked questions over result evaluation

8 hours ago
‘It’s never not going to hurt’: Janhvi Kapoor reveals her dreams of late mother Sridevi | Bollywood News

‘It’s never not going to hurt’: Janhvi Kapoor reveals her dreams of late mother Sridevi | Bollywood News

9 hours ago
Over 3,000 bottles of codeine-based cough syrup seized in Gonda

Over 3,000 bottles of codeine-based cough syrup seized in Gonda

9 hours ago
Trent’s Ambitious Growth: Noel Tata Confident of 10x Revenue, Global Expansion for Westside, Zudio

Trent’s Ambitious Growth: Noel Tata Confident of 10x Revenue, Global Expansion for Westside, Zudio

10 hours ago
FPI Outflows Surge to Rs 33,000 Crore in May on Rupee Depreciation, Global Shifts

FPI Outflows Surge to Rs 33,000 Crore in May on Rupee Depreciation, Global Shifts

10 hours ago
Sunday, May 31, 2026
  • PRESS RELEASE
  • ADVERTISE
  • CONTACT
  • Game
India News Online
  • Home
  • News
    • India
    • Punjab
    • International
    • Entertainment
  • Hindi News
  • Politics
  • Health
  • Business
  • Sports
  • Technology
  • Lifestyle
  • Video
    • All
    • Hindi Songs
    • Punjabi Songs
    पियवा किसनवा 90’S Old Hindi Songs🥰 90s Love Song😍 Udit Narayan, Alka Yagnik, Kumar Sanu songs Hindi

    पियवा किसनवा 90’S Old Hindi Songs🥰 90s Love Song😍 Udit Narayan, Alka Yagnik, Kumar Sanu songs Hindi

    90s Bollywood Wedding Songs | Evergreen Bollywood Hits | Shadi Song | Sadabahar Hindi Songs Jukebox

    90s Bollywood Wedding Songs | Evergreen Bollywood Hits | Shadi Song | Sadabahar Hindi Songs Jukebox

    आज तो बाल बाल बच गया😄90’S Old Hindi Songs🥰 90s Love Song😍 Udit Narayan, Alka Yagnik, Kumar Sanu song

    आज तो बाल बाल बच गया😄90’S Old Hindi Songs🥰 90s Love Song😍 Udit Narayan, Alka Yagnik, Kumar Sanu song

    भाभी ने बचाई ननद की जान 😆 90’S Old Hindi Songs 🥺90s Love Song 😍Udit Narayan, Alka Yagnik, Kumar

    भाभी ने बचाई ननद की जान 😆 90’S Old Hindi Songs 🥺90s Love Song 😍Udit Narayan, Alka Yagnik, Kumar

    Cold Rude boy falling for cute girl 💕 korean mix hindi songs 💞 Chinese mix hindi songs

    Cold Rude boy falling for cute girl 💕 korean mix hindi songs 💞 Chinese mix hindi songs

    90s हिंदी सदाबहार गीत | 90’s Romantic Hindi Songs | 90’s सदाबहार फिल्मी गाने | 90’s Bollywood Songs

    90s हिंदी सदाबहार गीत | 90’s Romantic Hindi Songs | 90’s सदाबहार फिल्मी गाने | 90’s Bollywood Songs

    90’S Old Hindi Songs🥰 90s Love Song😍 Udit Narayan, Alka Yagnik, Kumar Sanu songs Hindi Jukebox

    90’S Old Hindi Songs🥰 90s Love Song😍 Udit Narayan, Alka Yagnik, Kumar Sanu songs Hindi Jukebox

    90’s हिंदी गाने | 90’s Evergreen Songs | 90s सदाबहार गाने | Hindi Gana | 90’s Hit Songs | Durga Boss

    90’s हिंदी गाने | 90’s Evergreen Songs | 90s सदाबहार गाने | Hindi Gana | 90’s Hit Songs | Durga Boss

    90’s पुराने गाने | 90’s Evergreen Bollywood Hits | Old is Gold Collection | Hindi Sadabahar Gaane

    90’s पुराने गाने | 90’s Evergreen Bollywood Hits | Old is Gold Collection | Hindi Sadabahar Gaane

  • Travel
  • Game
No Result
View All Result
India News
No Result
View All Result
Home Business

417 infra projects show cost overruns of Rs 4.77 lakh crore in Sep

by India News Online Team
November 13, 2023
in Business
0
417 infra projects show cost overruns of Rs 4.77 lakh crore in Sep
Share on FacebookShare on TwitterShare on Email


As many as 417 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.77 lakh crore in September this year, an official report said.

417 infra projects show cost overruns of Rs 4.77 lakh crore in Sep

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects worth Rs 150 crore and above, out of 1,763 projects, 417 reported cost overruns and as many as 842 projects were delayed.

“Total original cost of implementation of the 1,763 projects was Rs 24,86,402.70 crore and their anticipated completion cost is likely to be Rs 29,64,345.13 crore, which reflects overall cost overruns of Rs 4,77,942.43 crore (19.22 per cent of original cost),” the ministry’s latest report for September 2023 said.

 

According to the report, the expenditure incurred on these projects till September 2023 is Rs 15,44,600.67 crore, which is 52.11 per cent of the anticipated cost of the projects.

However, it stated that the number of delayed projects decreased to 617, if delay is calculated on the basis of the latest schedule of completion.

Further, it stated that for 298 projects neither the year of commissioning nor the tentative gestation period has been reported.

Out of the 842 delayed projects, 194 have overall delays in the range of 1-12 months, 190 have been delayed for 13-24 months, 323 projects for 25-60 months and 123 projects have been delayed for more than 60 months.

The average time overrun in these 842 delayed projects is 36.94 months.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems were among the other reasons.

The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.

It has also been observed that project executing agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.



Source link

Tags: costcroreinfralakhOverrunsprojectsSepshow
Share198Tweet124Send

Related Posts

Trent’s Ambitious Growth: Noel Tata Confident of 10x Revenue, Global Expansion for Westside, Zudio
Business

Trent’s Ambitious Growth: Noel Tata Confident of 10x Revenue, Global Expansion for Westside, Zudio

May 31, 2026
FPI Outflows Surge to Rs 33,000 Crore in May on Rupee Depreciation, Global Shifts
Business

FPI Outflows Surge to Rs 33,000 Crore in May on Rupee Depreciation, Global Shifts

May 31, 2026
Auto 2026 Honda City Hybrid Review: New Design, ADAS, 27.2 kmpl Efficiency And Premium Comfort
Business

Auto 2026 Honda City Hybrid Review: New Design, ADAS, 27.2 kmpl Efficiency And Premium Comfort

May 30, 2026
RBI’s Forex Transaction Gains Soar 52% in FY26, Balance Sheet Expands
Business

RBI’s Forex Transaction Gains Soar 52% in FY26, Balance Sheet Expands

May 30, 2026
Load More
  • Trending
  • Comments
  • Latest
9 Festivals to Celebratein August in India

9 Festivals to Celebratein August in India

August 8, 2025
Corruption cases against govt officials: SC bats for striking balance | Latest News India

Corruption cases against govt officials: SC bats for striking balance | Latest News India

August 5, 2025
Guru Randhawa – SIRRA ( Official Video )

Guru Randhawa – SIRRA ( Official Video )

July 1, 2025
Baharon Phool Barsao – Suraj – Rajendra Kumar, Vyjayanthimala – Old Hindi Songs

Baharon Phool Barsao – Suraj – Rajendra Kumar, Vyjayanthimala – Old Hindi Songs

0
Phool Maangu Na Bahaar Maangu – Video Song | Raja | Madhuri Dixit & Sanjay Kapoor

Phool Maangu Na Bahaar Maangu – Video Song | Raja | Madhuri Dixit & Sanjay Kapoor

0
Dil Ka Rishta Song – Aishwarya Rai,Arjun Rampal, Alka Yagnik,Udit Narayan,Kumar Sanu, Nadeem-Shravan

Dil Ka Rishta Song – Aishwarya Rai,Arjun Rampal, Alka Yagnik,Udit Narayan,Kumar Sanu, Nadeem-Shravan

0
Indian wrestling coaches must keep updating: Bentinidis

Indian wrestling coaches must keep updating: Bentinidis

May 31, 2026
India’s Triumph: Asian U20 Athletics Championships Medal Haul

India’s Triumph: Asian U20 Athletics Championships Medal Haul

May 31, 2026
Sunil Gavaskar advises Mumbai Indians to take ‘some time off’ amid reports of Hardik Pandya sacking: ‘Take a step back’

Sunil Gavaskar advises Mumbai Indians to take ‘some time off’ amid reports of Hardik Pandya sacking: ‘Take a step back’

May 31, 2026
India News Online

24x7 Online News From India
India News Online is your news, entertainment, music fashion website. We provide you with the latest breaking news and videos straight from the entertainment industry.

Categories

  • Business
  • Entertainment
  • Health
  • Hindi News
  • Hindi Songs
  • India
  • International
  • Lifestyle
  • Panjab
  • Politics
  • Punjabi Songs
  • Sports
  • Technology
  • Travel
  • Uncategorized
No Result
View All Result

Recent Posts

  • Indian wrestling coaches must keep updating: Bentinidis
  • India’s Triumph: Asian U20 Athletics Championships Medal Haul
  • Sunil Gavaskar advises Mumbai Indians to take ‘some time off’ amid reports of Hardik Pandya sacking: ‘Take a step back’
  • Home
  • Disclaimer
  • DMCA
  • Privacy Policy
  • Cookie Privacy Policy
  • Terms and Conditions
  • Contact

Copyright © 2021 - India News Online.

No Result
View All Result
  • Home
  • News
    • India
    • Punjab
    • International
    • Entertainment
  • Hindi News
  • Politics
  • Health
  • Business
  • Sports
  • Technology
  • Lifestyle
  • Video
  • Travel
  • Game

Copyright © 2021 - India News Online.